Remodeling Beverly Hills: Whole House Remodeling

Full interior gut and rebuild for Beverly Hills homes, from measured drawings through final inspection sign-off.

Minimalist high-end interior after a whole house remodel in Beverly Hills

A whole house remodel empties the building. The interior comes down to studs, and what goes back is a different floor plan with new mechanical, electrical and plumbing behind it. Remodeling Beverly Hills takes these on across Beverly Hills, and they are the largest thing we do.

This is the largest thing we do and the one where sequence matters most. Call (424) 766-1835 and we will walk the house, tell you what the structure will and will not allow, and give you a budget range in writing the same week.

What a full gut renovation includes

A whole house remodel is not a series of room remodels done consecutively. The systems get replaced as systems, which is the entire economic argument for doing it all at once. You open the walls once.

  • Selective demolition to studs and subfloor, with hazardous material testing first on anything built before 1980
  • Structural changes: removing bearing walls, adding beams and posts, new shear panels and hold-downs
  • Full repipe from the meter, typically copper or PEX depending on the run
  • Panel upgrade and complete rewire, with the circuit count a modern house actually needs
  • New HVAC. Ducted, mini-split, or a hybrid where ceiling height is tight
  • Insulation, drywall, and a Level 5 finish where the lighting will show every seam
  • Millwork, cabinetry, tile, stone, flooring, and paint

What the age of your house changes

Open living space in a Beverly Hills home after a full interior renovation

Pre-1940 homes in the flats

Spanish Colonial Revival and Mediterranean Revival houses south of Santa Monica Boulevard were built with lath and plaster, knob-and-tube wiring, galvanized supply lines and cast iron waste. All four of those get replaced. Plaster in particular changes the demolition plan, because it comes off dirtier and slower than drywall and it is worth deciding early whether original plaster gets preserved or replaced.

Post-war traditional

Homes from the late 1940s through the 1960s are usually straightforward frame construction on a raised foundation or slab. The common issues are undersized electrical service, no insulation in the walls at all, and single-pane steel or aluminum windows.

Mid-century post-and-beam

Trousdale Estates and the hillside tracts have exposed beam ceilings and glass walls with almost no shear capacity. You cannot run new ducting or wiring through a beam ceiling the ordinary way, and adding lateral bracing without closing off the glass takes engineering rather than framing.

Sequence and schedule on a Beverly Hills gut

Design and engineering usually runs eight to sixteen weeks depending on how much structural work is involved. Plan check at the Beverly Hills Community Development Department follows, and an addition or a structural change adds review cycles that an interior-only scope does not.

Construction on a typical 3,000 to 5,000 square foot house runs six to twelve months. The critical path is almost never framing. It is cabinetry lead time, stone fabrication and the inspection calendar. We book rough inspections against a published schedule instead of calling for them once the work happens to be ready.

Budget planning that holds up: set aside 10 to 15 percent as a contingency on a pre-1970 house. Not because the scope is wrong, but because nobody knows what is behind a 1928 plaster wall until it is open.

Living arrangements during the work

A whole house gut is not a project you live through. There will be weeks with no water, no power, or no roof, and an occupied site slows a crew enough that the schedule extension usually costs more than the rental would have. We say this plainly at the estimate stage so it lands in the budget rather than as a surprise in month two.

Where owners do stay, it is normally because the scope is phased: one wing at a time, with a temporary kitchen and a hard dust barrier. That is a legitimate approach and we build it that way when asked, but it adds time and it costs more per square foot than doing the house all at once.

Talk to a Beverly Hills remodeling contractor

On-site estimate, straight answers on budget and schedule, and a written scope before anyone swings a hammer.

Call (424) 766-1835

Frequently asked questions

How much does a whole house remodel cost in Beverly Hills?

Broadly $200 to $800 per square foot as of 2026. A cosmetic-heavy renovation on a sound house lands low in that range; a full gut with structural changes, new systems and high-end finishes lands at the top or beyond it. The variables that move the number most are how much of the plumbing and electrical is being relocated, and finish level.

Is it cheaper to remodel or to tear down and rebuild?

It depends on what you are keeping. Once you are replacing the roof, the foundation is inadequate, and more than about half the framing is coming out, a rebuild is often cheaper per square foot and gives you a modern envelope. Where the existing structure is sound and the lot is constrained by current setback rules, remodeling keeps grandfathered conditions a new build would lose.

Do you handle the design, or do I need an architect first?

We work either way. We can take a set from your architect and build it, or handle design and engineering in-house as a design-build contract. On a whole house, design-build tends to save time mainly because the constructability questions get answered while the drawings are still editable.

What happens if you find something unexpected behind the walls?

It gets documented, priced and approved as a written change order before the work happens. On older homes the common ones are failed cast iron waste lines, knob-and-tube still energized, termite damage in a bearing wall, and a foundation that needs work. That is what the contingency is for.

How long will my whole house remodel take?

Plan on six to twelve months of construction for a typical Beverly Hills home, plus two to four months ahead of that for design, engineering and permits. Anyone quoting a full gut in three months is either leaving something out of the scope or has not been through plan check.